fiberglassSelf leveling groundSelf leveling plain surface treatment
①The basic plain ground shall be based on cement powder smooth surface or grinding stone ground;
②Natural land requires health preservation28Above the day, water is required8%If there are any unevenness or hollowing on the construction site, they must be removed;
③Fill the ground with epoxy mortar;
④The oil stains on the bare land need to be thoroughly cleaned;
⑤Before construction, it is necessary to keep the construction site dry and clean;
Self leveling groundundercoat
①Before construction, it is necessary to keep it clean. If any debris adheres, it should be removed. Mix the main agent and hardener in the correct proportion and stir thoroughly;
②Adjust the viscosity appropriately according to the ground conditions to complete the material mixing4Construction completed within hours
③The curing time for the bottom coating is about8More than hours.
Intermediate coating
①Before construction, it is necessary to keep it clean. If any debris adheres, it should be removed. Mix the main agent and hardener in the correct proportion and stir thoroughly;
②Add an appropriate amount of mixed resin to quartz sand;
③Apply the material evenly with a trowel;
④Materials need to be mixed for completion30Construction completed within minutes;
⑤Ensure proper handover handling at the construction handover point;
⑥The curing time of the intermediate coating is about8More than hours.
Batch soil layer
①Mix the main agent and hardener in the correct proportion and stir thoroughly;
②Apply the material evenly using a batch knife;
③Materials need to be mixed for completion30Construction completed within minutes;
④The soil curing and hardening time is about8More than hours;
⑤According to the actual needs, the construction should meet the requirements of being flat without holes, without batch knife marks or sanding marks.
Self leveling groundtop coat
①Before construction, it is necessary to keep it clean and remove any debris adhering to it;
②Stir the main agent evenly before use;
③Mix the main agent and hardener in the correct proportion and stir thoroughly;
④Use a roller or trowel to evenly apply and mix the material to complete the material30Construction completed within minutes;
⑤Handover handling should be done well at the construction handover point;
⑥After the construction is completed,24Can be accessed in hours,72Heavy pressure can only be applied after hours250CThe opening time should be appropriately extended at low temperatures.